60 days in advance! Successfully achieved the topping out of the steel structure project of Mingguang Village renovation project in Haidian District, Beijing

Date:2025/4/27 8:59:03 Popularity:12

On March 31st, with the last steel component of the steel structure being lifted into place, the steel structure project of Mingguang Village Renewal and Renovation Rental Housing Project (Plot 2) in Haidian District, Beijing, undertaken by Zhongnan Green Construction, successfully completed the topping out of the main structure, which was 60 days ahead of the planned topping out time.

640 (2).png

The picture shows the real scene of the main structure of two steel structure buildings

The Mingguang Village renovation project is located in Haidian District, Beijing, with a total construction land area of approximately 59300 square meters and a total construction area of approximately 250700 square meters. Zhongnan Green Construction has undertaken the construction of two steel structure buildings on plot 2 of the project. One of them is a 12 story apartment building with 3 underground floors, with a building height of 40.85 meters and a building area of approximately 11820 square meters. The other is a comprehensive building with 6 ground floors and 3 underground floors, with a building height of 23.8 meters and a building area of approximately 7140 square meters. The project is a key construction project in Haidian District, and upon completion, it will further enhance the modern urban appearance of Haidian District.


640 (3).png

The Mingguang Village renovation project is located in Haidian District, Beijing, with a total construction land area of approximately 59300 square meters and a total construction area of approximately 250700 square meters. Zhongnan Green Construction has undertaken the construction of two steel structure buildings on plot 2 of the project. One of them is a 12 story apartment building with 3 underground floors, with a building height of 40.85 meters and a building area of approximately 11820 square meters. The other is a comprehensive building with 6 ground floors and 3 underground floors, with a building height of 23.8 meters and a building area of approximately 7140 square meters. The project is a key construction project in Haidian District, and upon completion, it will further enhance the modern urban appearance of Haidian District.

640 (4).png

In response to the current situation of winter construction, the project management team has effectively formulated various safety measures, strictly implemented various safety management systems and inspection and supervision mechanisms, implemented and assessed safety responsibilities to every management cadre and team leader, and refined safety assessments to every worker, so that the construction site always maintains a civilized and safe construction standard state, ensuring safe construction throughout the cold winter and continuous day and night operations. It has been highly praised by the Party A, the general contractor, and the local security inspection department. The two steel structure construction projects undertaken by the company will be fully completed in April this year, and will be delivered ahead of schedule as high-quality projects, striving to make positive contributions to the economic construction of the capital.