After 22 consecutive days and nights of hard work, Zhongnan Green Construction Group has completed the installation of the main structure of the steel structure of the final assembly plant of the Haier Jiaozhou Refrigerator Intelligent Manufacturing (Phase I) project with a construction area of over 80000 square meters ahead of schedule. The early completion of the construction and installation of this project demonstrates Zhongnan's speed and has received unanimous praise from Jiaozhou municipal government departments, construction units, supervision units, and general contracting units.

The overall project rendering is shown in the picture
The Haier Jiaozhou Refrigerator Intelligent Manufacturing (Phase I) project is a key project in Shandong Province, located in Jiaozhou City. After completion, it will comprehensively lead the development of the home appliance industry and become a leading high-end intelligent home appliance production highland in China and internationally. The total construction area of the project is about 240000 square meters. The project consists of five factories: the final assembly plant, the module self-made plant, logistics center one, logistics center two, and the hazardous chemical warehouse.

The picture shows the scene of steel beam hoisting in the final assembly plant

The picture shows a panoramic view of the construction of the final assembly plant
According to the owner's requirements, the main structure construction and installation of the final assembly plant must be completed before November 15th. The construction period is the command. The project management team quickly completed all the preparations before the installation of the steel structure. The lifting started on October 18th and after 22 consecutive day and night operations, the installation of the steel structure main body of the final assembly plant was successfully completed on November 8th, one week ahead of the owner's required milestone goals. In order to complete the installation of the main structure within the deadline, the project management team has identified key nodes, optimized the lifting sequence, accurately calculated the construction period, and refined the construction tasks into daily clearing plans; At the same time, strict safety and quality management should be implemented, with safety responsibilities and quality control assigned to individuals at different levels. A large number of safety production facilities should be invested, and detailed quality management systems and corrective plans should be formulated to ensure safe and high-quality construction.

The picture shows the scene of company leaders guiding homework on site
The steel structure engineering of Haier Jiaozhou Refrigerator Intelligent Manufacturing (Phase I) project is another major project of Haier Group after the company inherited the construction of Haier Drum Interconnected Factory project and Haier High end Special Refrigerator project. As a long-term partner of Haier Group, the company attaches great importance to every project of Haier Group. With the key support of the company's leadership and the full efforts of on-site management and construction personnel, the main structure of the project was completed ahead of schedule, creating favorable conditions for Haier Group to achieve its strategic development plan.