Engineering Report | The Huaneng Yuhuan Power Plant Coal Yard Closed Renovation Grid Project, undertaken by Zhongnan Green Construction Group, has been successfully completed

Date:2022/11/28 9:02:23 Popularity:52

Recently, the closed renovation network structure project of the Yuhuan Power Plant coal yard constructed by Zhongnan Green Construction Group has successfully passed the completion acceptance.

微信图片_20221130090347.png

The overall project rendering is shown in the picture


This project is located within the Huaneng Power Plant in Yuhuan City, Taizhou City, Zhejiang Province. The project is divided into two phases, with a total construction area of over 130000 square meters. Both Phase I and Phase II consist of two closely connected grid coal sheds, with a maximum single span of approximately 112 meters; The grid structure adopts a positively placed four corner cone three center circular surface bolt ball node structure, supported by external chords, with a total of 11 zones. The project officially started construction on April 8, 2022. After more than 6 months of careful construction, it was completed on October 15 and successfully passed the final acceptance on October 30.


微信图片_20221130155909.png

The picture shows the on-site environment during construction

微信图片_20221130155920.png

The picture shows a night work scene


In the implementation of the project, due to the construction site serving as a fuel coal storage yard for power generation, daily production and construction operations are carried out simultaneously, resulting in a very narrow area available for construction operations. For this reason, the company's leadership attaches great importance to it, and the project management team strictly follows the construction plan verified by experts to carry out operations. Through systematic control, standardized operations, and good coordination and communication work, various difficulties such as tight time and narrow site have been successfully overcome, ensuring daily production and construction safety and ensuring project construction progress.


555.png

The picture shows a partial scene when the second phase of the project is completed

666.png

The picture shows the panoramic view after the completion of the project


The completion of the coal yard closure and renovation project will be dedicated to improving the regional air environment, helping Taizhou City win the battle for blue skies, protecting green mountains and waters, and is also a positive contribution made by the company in response to the national "dual carbon" and energy conservation and emission reduction policies.